In Chugach Federal Solutions, Inc., ASBCA Nos. 62712, et al., the Armed Services Board of Contract Appeals held that a contractor could recover its costs for having to quarantine personnel in accordance with government-imposed COVID safety requirements, because the underlying contract contemplated that the contractor would be compensated for complying with any changes to health and safety requirements.